Soil Levy Works.

Completed 12th hole.



12 hole before work.






9th before work to reshape and repair.








Receiving the 3,000 cubic meters of soil from the recent Northbridge oval upgrade has been fantastic. Since December we have been super busy transporting the soil, spreading, shaping and turfing it.





9th after remodeling work.



The area of fairway at the front of the 12th fairway was a particularly difficult site to fix up, having to deal with the redirection of large amounts of overland runoff and a maze of water holding rock shelves. This job alone would have cost $55,ooo with approx $40,000 being for soil.I am quite pleased with the results.









Allan doing some lovely turfing.



The other areas that have been repaired / returfed are the right side of the 1st fairway, the left and right roughs of the 7th hole, the right side of the 8th rough, the left and right sides of the 9th as well as the big area (1800m2) in front of the 9th tee.







We are finishing off all work returfing areas on the 12th hole, right and left sides of the rough before moving to the left of the 14th fairway.